20% of the Eastern Internal Regional Road (Fly Over) of Thessaloniki has already been completed, according to an update from the Ministry of Infrastructure and Transport, which also stressed that work is progressing according to the timetable, which foresees that the project will be delivered on May 16, 2027.
The construction of the aerial ring road of Thessaloniki for a total amount of €373.2 million is being constructed by the consortium AVAX-Mytilineos.
More specifically, the Ministry of Infrastructure and Transport announces that following the delivery, to the Private Partnership Entity, of all the land necessary for the construction of the project, the contractor construction consortium has developed a wide construction site along the entire length of the Eastern Internal Regional Road of Thessaloniki.
In addition, following the implementation of the approved traffic regulations, work is being carried out at a particularly rapid pace along the greater length of the construction site.
Indicatively, earthworks are in full swing, and small and medium technical and hydraulic works are being constructed. At the same time, the construction of major technical roofing works such as Cut and Cover [T8], [T15], and [T21] in the area of Constantinopolitika, as well as in the area before the bridge over the Superhighway, has started and is in progress.
For the construction of the Overpass Expressway, which is the bridge (flyover) of approximately four (4) kilometers, the rolling metal stretcher (formwork), which will be used for concreting, is being installed, which will be moved hydraulically along the entire project, on top of the platforms already under construction.
For this reason, the construction of the foundation shafts and the bridge footings (flyover) is being preceded by the construction of the bridge foundations, and concreting work is expected to start in March.